Office of Facilities


Parking Deck II and Surface Lot

Parking Deck

Description:

This project is for the design-build of an approximately 250,000 Sq. Ft. parking deck to serve current and planned residential housing, special events, and guests.  Construction will be on the current Lot L site with an estimated construction budget of $24,000,000.

UNCW Project Manager:

Lisa Seifert

FacilitiesACS@uncw.edu

Design-Build Contractor: Balfour Beatty Construction LLC, Raleigh, N.C.
Current Status: Construction
Estimated Completion Date: July 2020
Project Schedule:

Start of Construction - Mid-May 2019

HUB Opportunities: facilitiesacs@uncw.edu

Construction
Update:

Construction of the new Parking Deck continues in September with deliveries of oversized materials to the site.  The crane delivery will begin on Thursday, 9/12/19, and will include 10-15 loads of varying sizes.  Pre-cast concrete structural beams and columns will begin arriving the following week of 9/16/19. Deliveries will continue at 8-10 trucks per day, 6 days per week until completed in January.  Oversized loads must travel during daylight hours. 

A map of the delivery route shows that trucks will enter the campus on Hurst, travel thru the Greene track gravel lot to a temporary road then left onto Riegel Road and into the construction site.  The route is currently well marked with barricades between the gravel lot and Riegel Road,

Thanks for your patience with construction as we add more parking for our campus.