seahawk 1 cover

Project Schedules

Date Milestone
12/02/2015 Contract with Moore Foundation Start Date
02/23/2015 Subcontract with Cloudspace Instruments for Senor Design and Construction
02/26/2015 Subcontract with Clyde Space for Construction of 2 custom CubeSate Satellite Busses
08/05/2015 Meeting between Sensor and Satellite Design Teams in Glasgow, Scotland
08/06/2015

Small Satellite Conference in Logan, Utah

8/17-18/2015 Design Consultation @ Goddard Space Flight Center
4/20-20/2016

PDR: Preliminary Design Review @ Clyde Space in Glasgow, Scotland:

a. Freeze top-level design and specifications.

b. Agree/determine need for any prototyping

11/2016

CDR: CRITICAL DESIGN REVIEW

Cloudland Instruments in Santa Barbara, CA.

State of Flight Model Manufacture:

Clyde Space: Final Bus Design Completed and Agreed

Cloudland: Final Payload Design.

TBD

TRR: TEST READINESS REVIEW

TBD EVT: Environmental Test
TBD

TRB: TECHNICAL REVIEW BOARD

To complete acceptance

TBD

DRB: DELIVERY REVIEW BOARD

Delivery of 2 fully integrated and tested SeaHawk

TBD

CCD: CONTRACT COMPLETION DATE

2 Flight Ready and Bench Calibrated Seahawk CubeSats with integrated HawkEye Ocean Color Sensors.

TBD

AFT: AIRCRAFT FLIGHT TEST

HawkEye Pre-Launch Calibration

TBD LAUNCH
TBD

MISSION LIFETIME

18+ months

** TENTATIVE OR UNKNOWN DATES

Last Update: 06/22/2016