Summary Report and Recommendations:
Business Support Infrastructure for Sponsored Projects
Stuart Borrett
Associate Provost for Research and Innovation
Nate Miner
Associate Provost for Administration and Resource Management
November 15, 2022, Updated May 2023
In December 2018, the Carnegie Classification of Institutions of Higher Education reclassified the University of North Carolina Wilmington as a Doctoral University: High Research Activity (R2). In response to that recognition, the Chancellor convened a taskforce of institutional stakeholders to assess the campus impact of our R2 status on culture, identity, and current practices/processes. The Doctoral Transition Taskforce (DTTF) met during the summer and fall 2019 to develop recommendations related to their charge.
To add additional context to these recommendations, the Embracing R2 5-point Implementation Plan was established in 2020 and a committee of faculty and administrators met during the 2020-2021 academic year to build upon the work of that DTTF. The subcommittee on Building Research Infrastructure (point 5) built a draft model to address business administration support for funded projects. The subcommittee further made the following recommendation:
Charge a workgroup including staff members from college-level administration, the Center for Marine Science, departments/schools, SPARC, and AARM to develop a Business Administration Support Model (BASM) for funded projects leveraging the framework developed below. The intent is to create a model with well-defined roles and associated responsibilities with clearly established communication to ensure that we can best facilitate funded projects.
Since this recommendation, the SPARC office has undergone an internal audit which resulted in 18 findings - many of which center on achieving clarity in roles and responsibilities. Moreover, the peer review conducted through the recently completed NORDP evaluation also supports the need to achieve clarity.
In a memo dated August 25, 2022, the Provost provided a charge to explore the business support infrastructure within Academic Affairs for sponsored projects. That charge specified the following activities:
This report presents results of this work. This effort generally focuses on the post-award activities related to administering a sponsored program at UNCW.
In determining how to align responsibilities associated with the administration of sponsored programs, the following guiding principles were applied.
To the greatest extent possible, the alignment of responsibility out to:
General terms and definitions for research administration and sponsored projects are collected in “Definitions for Research Administration” document for ease of reference, which is maintained by the Sponsored Programs and Research Compliance office. The following definitions are also critical to understanding the university business support for sponsored programs.
Contract: Exchange of funds for the performance of a specific scope of work, usually written by the contracting agency. A contract is generally associated with procurement rather than financial assistance.
Cooperative Agreement: Similar to a grant but with more substantial involvement between the grantor and grantee.
Grant: An award of financial assistance to allow for the performance of certain work envisioned by the university or principal investigator.
Sponsored Project: Exchange transaction, generally in the form of a grant, cooperative agreement, or contract with a defined scope of work, specified budget, specific deliverables, and typically subject to audit and compliance requirements. Usually initiated by funding agency or sponsor through a program announcement or other type of solicitation.
SPARC: The Sponsored Programs and Research Compliance Office at UNCW that provides institutional sponsored program administration and support including assisting Principal Investigators with identifying funding sources, assisting with proposal development, overseeing the responsible management of sponsored projects, and ensuring university compliance with contract and grant fiscal and regulatory requirements related to sponsored programs.
Administrative Department/Unit: An established organizational structure that has a financial organization where a fund can be administered and sufficient support infrastructure to facilitate and execute operational responsibilities exists.
Principal Investigator (PI): An individual designated by the grantee and UNCW to direct a project or activity being supported by a sponsored project. A project Principal Investigator is responsible for leading the preparation, conduct, and administration of a research grant, cooperative agreement, training or public service project, contract, or other sponsored project. See UNCW Policy 09.007 Principal Investigator Responsibilities for Sponsored Projects for more detail.
Project Director (PD): A title used by some sponsors that is a synonym for Principal Investigator.
Co-Principal Investigator (Co-PI): When multiple PIs share authority for leading and directing the project, intellectually, logistically, and financially, they are designated as Co- Principal Investigators (Co-PIs). Each Co-PI is responsible and accountable for the proper conduct of the project, including the submission of all required reports. The designation of multiple/co-PIs for a single project diminishes neither the responsibility nor the accountability on any individual PI. One of the multiple PIs must be designated as the Contact Principal Investigator. [Constant with NSF PAPPG17-1 Exhibit II-7]
Common Set of Responsibilities
An initial collection of responsibilities was constructed through exploration of other UNC system campus support materials and input of stakeholders through the process used to address this charge. This Common Set of Responsibilities was utilized to assess the current perceptions of college/CMS stakeholders regarding the assignment of roles to specific responsibilities and to identify variance among these stakeholders.
This set of responsibilities primary focuses on post-award support activities; however, as part of the recommendations associated with this report, additional post-award and pre-award activities could be added to provide a more comprehensive view of activities necessary to administer sponsored projects.
Using the Common Set of Responsibilities, stakeholders were asked to engage in a four-part input/feedback process.
Available Selection | Definition |
---|---|
PI/PD | This is the individual (often a faculty member) who received the grant. |
Admin Unit | This selection should be used if the responsible role is a member of the College staff, Center staff, department/school staff, or similarly situated position. |
SPARC/Research | This selection should be used if the responsible role is a member of the SPARC office, central research office, or some other central unit (such as a unit inFinance). |
Varies | This selection should be used if the responsible role varies by project/program (i.e. for one project the Admin Unit staff might complete the task but in other projects SPARC/Research completes the task). |
Not defined/Unsure | This selection should be used if the responsible role has not been defined or ifyou are unsure. |
Everyone | This selection should be used if you believe the task/responsibility ought to be moved to the section for "responsibilities held by everyone". |
Multiple | This selection should be used if the task/responsibility is not refined enough to make one of the selections above and should be further refined/revised. |
Stakeholders Included in this process included the College and Center Business Officers and Assistant Deans for Administration and Resource Management, as well as the SPARC Director, Pre-Award Manager, and Post Award Manager.
Common Set of Responsibilities and Current Perceptions
Appendix A provides the final recommendations for the assignment of responsibilities to a responsible unit based on the outcome of the stakeholder engagements. As indicated earlier in the report, this set of responsibilities is focused on the post-award business administration processes within the division of Academic Affairs. We expect, however, that the clarification presented in this report to have a significant positive impact on operations and administration of sponsored programs. We further recommend continued review and clarification of additional roles and responsibilities related to administering sponsored programs. For example, at UNCW the Controller’s Office in Business Affairs is responsible for most sponsored program billing rather than SPARC and further clarifying this collaboration may be beneficial.
Responsibilities assigned to SPARC
Included in the recommendation column in Appendix A are those specific responsibilities assigned to SPARC based on this initial common set of responsibilities.
In general, SPARC is responsible for ensuring the university remains in compliance with federal and state policies pertaining to research. The office accepts funds provided to the university and is accountable for the legal compliance with sponsor (federal, state, local and private sources) regulations and policies. SPARC is the contact point for federal and state audits, both fiscal and programmatic, on contracts and grants related to sponsored programs. Additionally, SPARC currently administers two internal grant programs (Cahill Awards and Momentum Funds), as well as the return of F&A to departments.
Responsibilities assigned to Principal Investigators (PIs) or Project Directors (PDs)
Included in the recommendation column in Appendix A are those specific responsibilities assigned to PIs based on this initial common set of responsibilities.In general, a project PI/PD is the intellectual lead and overall project manager for a sponsored program. They are responsible for leading the preparation, conduct, and administration of the sponsored program.
Responsibilities assigned to Administrative Units
Included in the recommendation column in Appendix A are those specific responsibilities assigned to the sponsored program administrative unit on this initial common set of responsibilities.
Every sponsored program at UNCW has an identified administrative unit for the project or program. As considered by the assembled stakeholders, different administrative units at UNCW may vary in how they achieve the responsibility. In some instances, the needs may be met at the named department level, and in others it may be provided by an organizational parent unit (e.g., College or School).
Role and Responsibility Perception Variance
At the beginning of this process, there appeared to be large variance in the stakeholder perceptions of the roles and responsibilities related to administering sponsored programs at UNCW. We also discovered varied understanding of the many responsibilities.
In reviewing initial perceptions across the various stakeholders and the initial recommendations, the following general areas were identified with higher variance:
In the reconciliation process, the stakeholders were able to further reduce this variability in perceptions.
In summary, the deliberative processes described in this report increased the common understanding of the roles and responsibilities amongst the stakeholder representatives, clarified many process steps, and reduced the overall variance in perceptions. Establishing a campus-wide collective understanding if the final recommendations will require differing levels of engagement with PIs, unit administrators, and SPARC personnel.
This report summarizes what we characterize as both a discovery and developmental process. In this process, UNCW has already made progress toward process clarity in some responsibilities among the assembled stakeholders. In synthesizing the information collected through this process, the institutional has reached a level of maturity where the recommendation articulated by the Embracing R2 committee is no longer applicable. Instead, to create consistent, efficient, and equitable outcomes for projects, project personnel, and support staff, we make the following recommendations:
Responsibilities | Group | Responsible Stakeholder(s) |
---|---|---|
Communicate with SPARC Grant Officer throughout project | Everyone | |
Provide support to PIs for general questions | Everyone | |
Support appropriate measures to achieve the goals of the grant | Everyone | |
Attend all award team meetings as scheduled | Everyone | |
Direct all inquiries about financial reporting to SPARC (postaward@uncw.edu) | Everyone |
Responsibilities | Group | Responsible Stakeholder(s) |
---|---|---|
Receive notice of intent to fund from sponsor | Intent to fund | SPARC/Research |
Forward notice of intent to fund to aor@uncw.edu (if received) | Intent to fund | Everyone |
Notify the PI that a notice of intent to fund was received with next steps | Intent to fund | SPARC/Research |
Receive award documents from sponsor | Award Receipt and Acceptance | SPARC/Research |
Forward award documents are submitted to aor@uncw.edu (if received) | Award Receipt and Acceptance | Everyone |
Notify the PI that award documents were received and next steps | Award Receipt and Acceptance | SPARC/Research |
Review terms and conditions of award - scope and deliverables (pre-execution of award documents) | Award Receipt and Acceptance | PI |
Confirm terms and conditions of award with PI- scope and deliverables (pre-execution of award documents) | Award Receipt and Acceptance | SPARC/Research |
Review terms and conditions of award - compliance/legal (pre-execution of award documents) | Award Receipt and Acceptance | SPARC/Research |
Negotiate the award terms and conditions (if needed) in consultation with the PI (for scope/deliverables), and OGC (if needed) | Award Receipt and Acceptance | SPARC/Research |
Confirm final terms and conditions of the award with the PI (if negotiation occurred) | Award Receipt and Acceptance | SPARC/Research |
Accept the terms and conditions of the award (signature authority) | Award Receipt and Acceptance | SPARC/Research |
Schedule and Facilitate a New Award Setup Meeting | Award Receipt and Acceptance | SPARC/Research |
Request risk fund by completing the risk fund form, obtain necessary approvals, and submit to aor@uncw.edu | Risk Funding (if needed) | PI |
Review of risk fund form, and if approved, initiate fund establishment | Risk Funding (if needed) | SPARC/Research |
Notify PI when risk fund when created and ready for use | Risk Funding (if needed) | SPARC/Research |
Request to establish banner GRANT fund(s) and establish the original budget(s) | Fund Establishment | SPARC/Research |
Review project for research compliance (COI, IRB, IACUC) | Fund Establishment | SPARC/Research |
Notify PI and Business Officer when fund is created and provide fund number | Fund Establishment | SPARC/Research |
Notify business officer if a COST SHARE fund(s) is needed | FE-Cost Share (if needed) | SPARC/Research |
Responsibilities | Group | Responsible Stakeholder(s) |
---|---|---|
Notify SPARC of subaward needs/requirements throughout the life of a project | PI | |
Lead subaward negotiation and agreement development (compliance/signature authority) | SPARC/Research | |
Provide input for subaward negotiation and agreement development (deliverables/scope) | PI | |
Execute (sign and deliver) subaward agreements | SPARC/Research | |
Initiate the fund establishment process for subaward (see above), if needed | SPARC/Research | |
Notify the PI and Business Officer when the final subaward agreement is signed | SPARC/Research | |
Notify the Purchasing Admin for the unit where the fund for the subaward is located | SPARC/Research | |
Assign subcontractor funds to proper budget line(s), if needed | SPARC/Research | |
Ensures sub awardee compliance with OMB Circular A-133 (subrecipient monitoring) | SPARC/Research | |
Ensure that sub awardee expectations are being met throughout the contract | PI | |
Notify SPARC if modifications are required to subawards agreements (including cancelation) | PI | |
Initiate a requisition for the sub awardee | Admin Unit | |
Receives invoices from sub awardees (subawards@uncw.edu) | SPARC/Research | |
Forward subaward invoice to subawards@uncw.edu (if received) | Everyone | |
Review subaward invoice for allowability, if allowable forward to PI | SPARC/Research | |
Confirm deliverables have been met to substantiate the invoice, signs, and returns to responsible office | PI | |
Approves payment of sub awardee invoices and attach to the PO for payment | Admin Unit | |
Ensure that Subcontract full deliverables met | PI | |
Ensure final invoice received as defined in the contract terms and conditions | SPARC/Research | |
Reconcile subaward payments against PO | Admin Unit | |
Liquidate subaward purchase order | Admin Unit |
Responsibilities | Group | Responsible Stakeholder(s) |
---|---|---|
Prepare technical reports (interim/annual/final) | technical reports | PI |
Submit technical reports to sponsor with copies to SPARC (if no AOR/certification signatures are required) | technical reports | PI |
Obtain required signatures for submission of technical (interim/annual/final) | technical reports | PI |
Submit technical reports to sponsor if AOR/certification are required (interim/annual/final) | technical reports | SPARC/Research |
MOVED TO PARKING LOT | financial reports |
Responsibilities | Group | Responsible Stakeholder(s) |
---|---|---|
Develop and communicate overall personnel plan for the project in alignment with the established project budget | personnel planning | PI |
Communicate personnel plan updates to project support team, as needed | personnel planning | PI |
Ensure that personnel actions are in support of the project, align with available funds based on the award, and can reasonably support the project given the timing of the action relative to the overall project timeline | personnel planning | PI |
Request the initiation of personnel actions in alignment with the personnel plan for the project | personnel planning | PI |
Verify that the personnel can be supported in the unit where they are proposed to be housed and the grant personnel are trained to serve as a supervisor (if needed) | personnel planning | Admin Unit |
Assure the appropriateness, reasonableness, and allowability of personnel actions in alignment with University requirements | personnel planning | Admin Unit |
Assure the appropriateness, reasonableness, and allowability of personnel actions in alignment with sponsor requirements | personnel planning | SPARC/Research |
Review and approve the request to initiate a hiring action based on department/College/Administrative Unit policy and practice | Hiring | Admin Unit |
Initiate the hiring process through the appropriate administrative process (e.g., PeopleAdmin, EPAF, FLAC) | Hiring | Admin Unit |
Conduct the hiring process in accordance with University policy and operational practice | Hiring | Admin Unit |
Collect the necessary paperwork to complete the hiring action | Hiring | Admin Unit |
Review and approve the request to initiate a people admin action based on department/College/Administrative Unit policy and practice | peopleadmin | Admin Unit |
Verify that sufficient budget exists in the fund to support the requested People Admin action (if budget is impacted) | peopleadmin | Admin Unit |
Ensure that the requested PeopleAdmin action is allowable based on sponsor requirements | peopleadmin | SPARC/Research |
Initiate the PeopleAdmin action based on operational practice | peopleadmin | Admin Unit |
Complete the PeopleAdmin action based on operational practice | peopleadmin | Admin Unit |
Review and approve the request to initiate an EPAF action based on department/College/Administrative Unit policy and practice | EPAF | Admin Unit |
Verify that sufficient budget exists in the fund to support the requested EPAF action (if budget is impacted) | EPAF | Admin Unit |
Ensure that the requested EPAF action is allowable based on sponsor requirements | EPAF | SPARC/Research |
Initiate the EPAF action based on operational practice | EPAF | Admin Unit |
Complete the EPAF action based on operational practice | EPAF | Admin Unit |
Review and approve the request to initiate an FLAC action based on department/College/Administrative Unit policy and practice | FLAC | Admin Unit |
Verify that sufficient budget exists in the fund to support the requested FLAC action (if budget is impacted) | FLAC | Admin Unit |
Ensure that the requested FLAC action is allowable based on sponsor requirements | FLAC | SPARC/Research |
Initiate the FLAC action based on operational practice | FLAC | Admin Unit |
Complete the FLAC action based on operational practice | FLAC | Admin Unit |
Issue time and effort reports - supports automated time/effort reports from Banner Effort Certification system | effort reporting | SPARC/Research |
Complete time and effort certification and submission | effort reporting | PI |
Verify the accuracy of effort reports for all project personnel, approves them, and submits them to SPARC by the deadline | effort reporting | Admin Unit |
Certify time/effort back to sponsor and any other reporting requirements | effort reporting | SPARC/Research |
Responsibilities | Group | Responsible Stakeholder(s) |
---|---|---|
Conduct expenditure reconciliation for posted transactions | Reconciliation | Admin Unit |
Conduct an overall reconciliation on a monthly basis to identify any posted transaction that was unexpected | Reconciliation | Admin Unit |
Prepare journal entries to correct expense accounting | Journal Entries | Admin Unit |
Prepare journal entries to correct revenue accounting | Journal Entries | SPARC/Research |
Reviews and Approves journal entries moving expenses/revenue to a grant or within a grant to ensure compliance to sponsor requirements | Journal Entries | SPARC/Research |
Ensure journal entries are submitted in compliance with University standards | Journal Entries | Admin Unit |
Prepare labor redistributions to correct expense accounting | Labor Redistributions | Admin Unit |
Reviews and Approves labor redistributions to a grant or within a grant to ensure compliance to sponsor requirements | Labor Redistributions | SPARC/Research |
Ensure labor redistributions are submitted in compliance with University standards | Labor Redistributions | Admin Unit |
Produce an "up to date" spending to budget report | Spending Reports | Admin Unit |
Distribution of spending to budget reports to the PI | Spending Reports | Admin Unit |
Review of spending to budget reports with the PI | Spending Reports | Admin Unit |
Facilitate all sponsor required budget reviews with the PI | Spending Reports | SPARC/Research |
Responsibilities | Group | Responsible Stakeholder(s) |
---|---|---|
Initiate requests with grant officer for project re-budgeting | PI | |
Request authorization to re-budget, if needed, with the sponsor | SPARC/Research | |
Execute appropriate budget revisions process | SPARC/Research | |
Assures budget actions align with sponsor requirements | SPARC/Research |
Responsibilities | Group | Responsible Stakeholder(s) |
---|---|---|
Initiate requests with grant officer for cost share re-budgeting | PI | |
Request authorization to re-budget, if needed, with the sponsor | SPARC/Research | |
Execute appropriate budget revisions process | Admin Unit | |
Assures budget actions align with sponsor requirements | SPARC/Research |
Responsibilities | Group | Responsible Stakeholder(s) |
---|---|---|
Develop an overall spending plan for the project in alignment with the established project budget | Expenditures | PI |
Maintain and update overall spending plan for the project in alignment with the established project budget | Expenditures | PI |
Request a spending activity in alignment with the overall spending plan for the project | Expenditures | PI |
Review expenditure request for compliance with sponsor requirements that expenses are in support of the project, align with the terms and conditions of the project, and can be reasonably utilized given the timing of the expense against the overall project timeline | Expenditures | SPARC/Research |
Ensure that sufficient funds remain in established budget pools to support expenditures prior to entering | Expenditures | Admin Unit |
Initiate request for travel and expense reimbursements | Travel/Reimbursement | PI |
Review and approve request to travel and expense reimbursements for compliance to sponsor requirements | Travel/Reimbursement | SPARC/Research |
Review and approve request to travel and expense reimbursements for compliance to university requirements | Travel/Reimbursement | Admin Unit |
Process actions for travel and expense reimbursements | Travel/Reimbursement | Admin Unit |
Liquidate encumbrances associated with travel and expense reimbursement actions | Travel/Reimbursement | Admin Unit |
Initiate request for purchases | Purchasing | PI |
Review and approve request to purchases for compliance to sponsor requirements | Purchasing | SPARC/Research |
Review and approve request to purchases for compliance to university requirements | Purchasing | Admin Unit |
Process actions for purchases | Purchasing | Admin Unit |
Receive item purchased and notification of receipt | Purchasing | PI |
Receive item in Ushop and process for payment | Purchasing | Admin Unit |
Liquidate encumbrances associated with purchases | Purchasing | Admin Unit |
Initiate purchase on pcard transactions | P-card | PI |
Works reconciliation for pcard transactions | P-card | Admin Unit |
Budget authority approval for pcard transactions | P-card | Admin Unit |
Grant Officer approval of pcard transactions | P-card | SPARC/Research |
Responsibilities | Group | Responsible Stakeholder(s) |
---|---|---|
Create and maintain resources related to the documentation standards of non-financial cost-share | SPARC/Research | |
Notify PIs of non-financial cost share obligations written into the award based on the proposal | SPARC/Research | |
Notify PIs business support team of non-financial cost share obligations written into the award based on the proposal | SPARC/Research | |
Develop a plan at the beginning of the program to ensure that non-financial cost-share obligations are met | PI | |
Identify non-financial cost share contributions through the execution of the project | PI | |
Prepare or collect documentation of non-financial cost share contribution | PI | |
Assures appropriateness, reasonableness, and allowability of non-financial cost-share are in compliance with University, College/Administrative Unit, and department/school requirements | Admin Unit | |
Notify SPARC of fulfilled non-financial cost share contributions through the submission of documentation | PI | |
Assures appropriateness, reasonableness, and allowability of non-financial cost-share are in compliance with Sponsor requirements | SPARC/Research | |
Upload documents related to non-financial cost-share contributions in OSPREY and Image Now | SPARC/Research | |
Transmit documents to sponsor related to non-financial cost-share as required or at project completion | SPARC/Research | |
Identify, calculate, document, and report waived F&A contributions to non-financial cost-share commitments | SPARC/Research | |
Verify that non-financial cost-share obligations are met at the close of the grant | SPARC/Research |
Responsibilities | Group | Responsible Stakeholder(s) |
---|---|---|
Charges F&A to the grant fund in proportion to expenditures for each budget period | SPARC/Research | |
Considers the effect on F&A (increase or decrease) for certain budget revision actions | SPARC/Research | |
Notifies and distributes the incentive share portion of F&A | SPARC/Research |
Responsibilities | Group | Responsible Stakeholder(s) |
---|---|---|
Ensure Banner billing parameters are setup according to the sponsor requirements | SPARC/Research | |
Notify SPARC of project completion milestone to initiate billing, if needed | PI | |
Determine amount to invoice sponsors as needed | SPARC/Research | |
Review and verify charges included in the invoice | PI | |
Issue invoices to sponsors (invoicing, letter of credit draw-downs, wire transfers, etc) | SPARC/Research | |
Reconciliation of invoices to payments | SPARC/Research |
Responsibilities | Group | Responsible Stakeholder(s) |
---|---|---|
Sends 180-day notice as reminder of award close-out procedures | SPARC/Research | |
Contact SPARC if a no-cost extension will be required for the project | PI | |
Develop a plan for all permanent status employees funded by the grant for the conclusion of the project | PI | |
Initiate timely notice to employees who will be discontinued at the conclusion of the project | Admin Unit | |
Develop a plan to ensure that all orders and purchases are received and invoiced by the close out date | PI | |
Develop a plan to ensure that all recurring expenditures to the project are redirected or canceled | PI | |
Develop a plan to ensure that all travel reimbursements and payments are completed prior to the project close out date | PI | |
Develop a plan to ensure that all deliverables and commitments are finalized prior to the project close out date | PI | |
Sends 90-day notice as reminder of award close-out procedures | SPARC/Research | |
Verify at 90-day notice that employee termination notification has occurred | Admin Unit | |
Sends 60-day notice as reminder of award close-out procedures | SPARC/Research | |
Sends 30-day notice as reminder of award close-out procedures | SPARC/Research | |
Sends communication (report/email/notice) that a grant is closing, that an extension is not being requested, and close-out actions need to be initiated | SPARC/Research | |
Modify all active jobs with an assignment end date after the project end date to be terminated by the project end date or moved to another funding source | Admin Unit | |
Verify that all orders and purchases are received and invoiced by the project close out date | Admin Unit | |
Verify that all recurring expenditures are either terminated or moved to another funding source | Admin Unit | |
Verify that all travel reimbursements and payments are completed prior to the project close out date | Admin Unit | |
Provide an overall report of expenditures posted to Banner for final review by the PI prior to the project close out | Admin Unit | |
Verify that all known financial commitments are expended in Banner | PI | |
Complete a final fund reconciliation to ensure that all transactions post by the project close out date and that all necessary fund corrections are initiated | Admin Unit | |
Verify that vacation payout posts to the appropriate funding source (need policy on this) with appropriate communication to payroll for processing transaction | ||
Initiate close-out checklist to ensure that all stakeholders are/have completing their required close-out actions | SPARC/Research | |
Verify that all deliverables have been met prior to the project close out date | PI | |
Maintains appropriate documents associated with deliverables including required data storage, sharing, and retention standards | PI |